1345 TURK STREET PROPOSED PROJECT SCHEDULE
Project Awarded to MSPDI | April 2007 |
Community Design Presentation | December 2007 – January 2008 |
Approval of Schematic Design by Redevelopment Agency Commission | February 2008 |
Design Development and Construction Documents Begin | Summer 2009 |
Conditional Use Granted by Planning Department | January 2010 |
Design Completes | February 2010 |
Developer Enters into a Development and Disposition Agreement with the San Francisco Redevelopment Agency | February 2010 |
Project Bidding and Permitting | March 2010 |
Neighborhood Construction Job Outreach Begins | June 2010 |
Construction Starts | July 2010 |
Project Information Workshops | Summer 2010- Spring 2011 |
Project Outreach to Certificate Holders | Spring - Summer 2010 |
Buyer Preparation and Homeownership Workshops | Summer 2010- Spring 2011 |
Buyer Lottery | Summer 2011 |
Construction Completes | December 2011 |
Project Move-In | January - March 2012 |