1345 TURK STREET PROPOSED PROJECT SCHEDULE

Project Awarded to MSPDI
April 2007
Community Design Presentation
December 2007 – January 2008
Approval of Schematic Design by Redevelopment Agency Commission
February 2008
Design Development and Construction Documents Begin
Summer 2009
Conditional Use Granted by Planning Department
January 2010
Design Completes
February 2010
Developer Enters into a Development and Disposition Agreement
with the San Francisco Redevelopment Agency
February 2010
Project Bidding and Permitting
March 2010
Neighborhood Construction Job Outreach Begins
June 2010
Construction Starts
July 2010
Project Information Workshops
Summer 2010- Spring 2011
Project Outreach to Certificate Holders
Spring - Summer 2010
Buyer Preparation and Homeownership Workshops
Summer 2010- Spring 2011
Buyer Lottery
Summer 2011
Construction Completes
December 2011
Project Move-In
January - March 2012